Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure Projects topic

No spam. Unsubscribe anytime.

Engineer: AMD phases advance; Chub Run to start Nov. 1, awaiting environmental clearances for Phase II/IV

Town of Nutter Fort Town Council · September 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Written engineering report said Phase I AMD pay-application comments were addressed, Phase II final design submitted with 28 of 34 ROWs obtained and environmental assessment pending from OSM; Chub Run start is scheduled for Nov. 1, 2025, and Phase IV forcemain work awaits WVDEP clearance.

The town’s engineer submitted a written report covering multiple projects. For Phase I AMD, pay-application comments have been addressed and the engineer said a special meeting might be requested to approve a requisition depending on comment-approval timelines.

Phase II AMD final design was submitted by Sept. 1, 2025; the report stated 28 of 34 right-of-ways are secured and the project awaits an environmental assessment clearance from the Office of Surface Mining (OSM) before it can go out to bid by year-end. Chub Run is scheduled to start Nov. 1, 2025; the engineer indicated a change order for a time extension will be presented next month. Phase IV forcemain work also awaits West Virginia Department of Environmental Protection (WVDEP) environmental clearance, and an engineering contract is being prepared for the Edison retaining wall project.