Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure topic

No spam. Unsubscribe anytime.

Bridge funding approved; Curtis Hollow Bridge work paused awaiting bearings

Steuben County Finance Committee · June 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee approved $155,000 increases for two county bridge projects and authorized transfers to prioritize work; public works said Curtis Hollow Bridge crews are delayed about a month because a single supplier of bearings is behind schedule.

The finance committee approved appropriations of $155,000 each for County Route 21 and County Route 46 bridge projects, moving funds from the bridge unassigned account to specific projects.

Public works also reported that Curtis Hollow Bridge work will pause for about a month because the supplier that produces the steel‑infused rubber bearings is backlogged. The director said crews remain on schedule when parts are available and that traffic control and local feedback have been positive so far.

Committee members asked whether the delays reflected contractor or county issues; public works said the delay is due to the supplier being "overbooked" and not a local scheduling problem.