Committee approves $3.03 million in CHIPS allocations for county roads and equipment
Summary
Steuben County approved $3,030,000 in allocations from CHIPS and related state funding to specific county routes, surface treatments and equipment, plus acceptance of additional state funding and rollovers totaling more than $1.6 million in one item; the committee also authorized surplus transfers to cover project cuts.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Public works told the committee the county received state funding and rollovers and asked the finance committee to accept and appropriate the amounts. The presentation listed $1,643,185.03 in rollover funds for CHIPS items, $12,803.87 for "Pave our potholes," $47,446.47 for Pave New York, and $853,307.06 for extreme winter recovery; the chair moved and the committee carried the acceptance.
For CHIPS allocations, the committee approved specific increases totaling $3,030,000 to be moved from the road improvement unassigned account into project‑specific accounts: County Route 1 (Burhollow) +$180,000; County Route 71 (North Jasper) +$80,000; County Route 702 (Dennis Corners) +$145,000; County Route 84 (Squab Hollow) +$300,000; County Route 95 (Day Road) +$100,000; County Route 106 (Church Creek) +$275,000; surface treatments +$700,000; major equipment +$1,000,000; County Route 4 (Kohakton) +$250,000.
Committee members asked whether the extra funds would cover escalation costs; public works said they will cover current escalation but earlier project cuts were still necessary. To manage cost increases, the committee authorized the transfer of $800,000 in surplus from three projects into the road improvement account and reductions to County Route 14 (‑$300,000), County Route 52 (‑$225,000) and County Route 87 (‑$275,000) to adjust the five‑year plan.
Public works cautioned that higher oil and asphalt costs forced reductions in chip seal mileage and trimming of some paving projects, and that the CHIPS formula is not published—they wait for the state letter showing allocations.