County accepts anticipated FAA and state grants for airport SRE building phase 2
Summary
Legislature approved accepting approximately $7 million in anticipated FAA and NYSDOT grants to fund phase 2 of a 5‑phase combined snow‑removal and rescue/firefighting (SRE) building at the county airport; the local share is about $178,467 from passenger facility charges and the vote was unanimous.
Get email alerts on the Infrastructure Grants topic
No spam. Unsubscribe anytime.
The Tompkins County Legislature voted to accept anticipated Federal Aviation Administration and New York State Department of Transportation grants to fund phase 2 of a five‑phase snow‑removal equipment and airport rescue/firefighting (SRE) building project at the county airport.
Chair Lee Shurtleff described the project as a roughly 46,000‑square‑foot facility in total; phase 2 will construct about 23,000 square feet for snow‑removal equipment. Shurtleff said anticipated FAA Infrastructure Investment and Jobs Act monies and an FAA Airport Improvement Program grant together with expected state matching funds would cover roughly $7,000,000 of the phase cost, with a local share of approximately $178,467 sourced from passenger facility charges. Legislators asked about long‑term operating costs and the prospect of vacated space once equipment is moved indoors; Shurtleff and colleagues said federal directives and airport master‑plan requirements largely drive the timing and scope.