Avon reviews excavation safety and right-of-way restorations after regional gas explosion

Council of the City of Avon, Ohio · July 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Following a regional gas explosion, Avon officials said a recent meeting with Columbia Gas, Brightspeed and contractors focused on ensuring safety, clearer utility markings, and improved restoration of disturbed lawns and landscaping in city rights-of-way.

Mayor Bryan Jensen opened discussion of right-of-way excavation practices after a recent Twinsburg Township gas explosion, saying the Administration convened a meeting with Columbia Gas, Brightspeed and Brightspeed subcontractors to address risks and coordination. "The gathering served an important purpose," Jensen said, introducing the Administration summary.

City Engineer Ryan Cummins, who attended the meeting, said participants exchanged views on protecting residents and ensuring restorations are completed promptly. He described the meeting as "very positive" and said Brightspeed and contractors expressed a willingness to be more proactive going forward. Cummins added that safety protocols and waiting for utility markings were discussed and, "to his knowledge, all safety requirements were being met."

Council members pressed on persistent complaints that contractors have failed to properly restore disturbed right-of-way areas such as grass and landscaping. Council Member Scott Radcliffe noted restoration concerns had been ongoing during the project; Cummins confirmed the issue was raised directly with Brightspeed and subcontractors and that the City's Service Department had frontline experience with resident calls. Council Member Jennifer Demaline asked whether utility lines were being properly marked before excavation; Cummins said Brightspeed generally waits for markings, and contractors noted delays in marking by the gas company as a source of frustration.

Council also discussed a second fiber company, Ripple Fiber, which the Administration said has not yet begun work and remains in review; Director Duane Streator and others recommended meeting with Ripple Fiber to review safety and restoration expectations before operations begin. The meeting produced no formal action at this session, but the Administration said it would continue to monitor contractor performance and emphasize right-of-way restorations.