Summary
Staff proposed WSP design work for urgent structural repairs to two downtown garages (design fee capped at $247,600) and an optional lighting design package (not‑to‑exceed $92,200); Council supported moving the structural work forward and asked staff for a clearer lighting scope and to account for prior Honeywell upgrades.
Get email alerts on the Garage Repairs topic
No spam. Unsubscribe anytime.
Planning staff brought forward two design engagements with WSP: structural repairs for both garages and a separate lighting design package. Carol Sammel (staff) said the structural design fee is estimated at $247,600 and the lighting design was presented with a not‑to‑exceed number of $92,200 for both garages as a maximum design fee.
Council members pushed for a clearer scope and asked staff to confirm prior work by Honeywell and to bring lighting testing and surface‑treatment options before committing to a large design fee. "The structural things, I think since we're ready to go ahead with that I think the 247,000 is the bare minimum structural improvements," Sammel said; she added the lighting package could be stepped back until the team provides a refined scope. Council agreed staff should return with a detailed lighting scope and refined estimates and authorized staff to prepare a structural‑repair resolution for the next meeting.
Members also discussed potential signage and cladding work to improve garage facades but asked staff to obtain additional pricing before moving those elements forward.