Fire department reported revenues $82,938 over budget through June and projected a record year in call volume; chief warned Station 2 could stall without a structural-steel delivery and asked to prioritize gear replacement and community risk‑reduction work.
Get email alerts on the Public Safety topic
No spam. Unsubscribe anytime.
The fire department reported midyear finances showing projected revenues ‘‘Right now, projected revenues are coming in $82,938 over budget, which is a good number.’’ The chief told trustees payroll was running about $43,342 over budget for the year so far, excluding a SAFER grant payment the department expects to receive later in the year.
Chief outlined current EMS coverage and staffing: during daytime the district runs with four full‑time members and part‑time staff that start at 10 p.m., with options to staff either two paramedic ambulances 24/7 or one ambulance plus an engine. He said call volume stood at 1,014 through June and the department expects to exceed 2,000 calls by year end, which would be a record year.
On capital needs, the chief identified a mandatory purchase of 22 full sets of structural firefighting gear, budgeted at $104,302 for 2027, and highlighted aging apparatus and rising fuel costs as risks to the year‑end outlook. He also warned that Station 2 construction could be delayed because the structural steel, manufactured locally, has no confirmed delivery date: ‘‘it is being manufactured here in DeForest, but they're not communicating very well. As of yet, we do not have a delivery date.’’
Trustees asked about staffing and funding offsets. The chief said four SAFER‑grant positions will be funded at 75% federal support and that ending rent payments on Station 1 (about $140,000/year) would help absorb Station 2 operational costs once it opens. No formal board action was taken; the presentation will inform final 2027 budget deliberations.