Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Stormwater topic

No spam. Unsubscribe anytime.

City awards $384,338 drainage and roadway improvement contract for NE 21st/NE 38th to JD Backhoe

Lighthouse Point City Commission · May 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works reported failing 60-year drainage infrastructure on NE 21st Ave/NE 38th St; the commission awarded JD Backhoe Inc. the $384,338.28 contract (plus 10% contingency) to replace pipe and repair road depressions, passing the resolution unanimously.

Public Works Director Duane Ackerbloom told the commission the drainage system for Northeast 21st Avenue and Northeast 38th Street is over 60 years old, installed in short riveted sections and now showing breaks that cause potholes and road depressions. He recommended awarding the project to JD Backhoe Inc. following the RFP and selection process.

Ackerbloom said the project cost is $384,338.28 with a 10% contingency ($38,433.83) and noted the work was included in the fiscal-year stormwater budget. Commissioners moved and approved Resolution 2025-2663 to award the contract; the motion passed unanimously 5-0. The director said work will target failing pipe sections and previous temporary patches will be replaced with a more durable installation.