Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Streets topic
No spam. Unsubscribe anytime.
Road resurfacing quotes put 1/2-street project on St. Stephen budget radar
Summary
City Engineer presented quotes for one street: $346,900 for full reconstruction and $303,600 to resurface; council will consider the figures at the budget meeting and continue patching older roads in the short term.
Get email alerts on the Streets topic
No spam. Unsubscribe anytime.
City Engineer Randy Sabart told the council July 2 that staff surveyed older, cracking streets and proposed patching short-term while planning a long-term project. For one identified corridor, the city received two contractor quotes: full reconstruction estimated at $346,900.00 and resurfacing estimated at $303,600.00. Councilmembers agreed to review the quotes further at the budget meeting.
Public works staff reported recent work on 9th Ave (gravel and blading) and ongoing pothole repairs; staff said the parking lot is holding up but the east side shows more wear. The council did not authorize immediate reconstruction; members directed staff to include the quotes in the upcoming budget discussion and to continue patching and maintenance in the interim.
