Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Bond 2022 topic
No spam. Unsubscribe anytime.
RFISD says new high school 77% complete, substantial completion expected Feb. 2026
Summary
Rockport-Fulton ISD trustees heard a construction update showing the new high school is 77% complete with $30.34 million authorized and a substantial completion date of February 2026.
Get email alerts on the Bond 2022 topic
No spam. Unsubscribe anytime.
Board members heard a monthly construction report for the Bond 2022 high school project that put the facility at 77% completion and listed $30.34 million authorized to date. TEAL Construction representative Michael Miller and Claycomb representatives Adam Feild and Will Foley told trustees the project’s substantial completion is scheduled for February 2026.
The trustees discussed a change in the high school completion date during the bond construction committee report. Trustee Logan Burton told colleagues the committee had walked the new campus and expressed excitement about the facility. The report did not include a revised final cost estimate beyond the $30.34 million figure presented. The board took no separate action on the construction update at the meeting.
