Kincaid board approves lower‑cost water‑tower inspection with Pittsburg Tank and Tower
Summary
After rescinding an earlier approval for a $4,100 inspection, trustees approved a $1,325 inspection by Pittsburg Tank and Tower. The board first voted to rescind the prior motion and then approved the lower bid by voice vote.
Get email alerts on the Water Tower topic
No spam. Unsubscribe anytime.
Mayor Pezze told the board he had contacted the firm that inspected the tower previously and reported a $1,325 bid from Pittsburg Tank and Tower, lower than the $4,100 KLM bid previously approved. He asked the board to rescind the earlier motion and approve the lower bid.
Trustee Nelson moved to rescind the previous approval; Dees seconded and the motion passed. Trustee Dees then moved to approve the $1,325 inspection with Pittsburg Tank and Tower; Nelson seconded and the board voted unanimously to accept the lower bid. The inspection will proceed and a structural report will follow.