Controller outlines IT RFP timeline and Lake Margrethe dam project; EPA grant work plan due mid‑July

Crawford County Board of Commissioners · June 26, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County Controller Paul Compo said Convergent will run the IT contract RFP (release July 31, proposals due Aug. 21, recommendations by Sept. 18). He reported the Lake Margrethe Dam work is complete and EPA grant forms are due July 15 with awards expected by the end of August for a four‑year grant starting Oct. 1, 2025.

County Controller Paul Compo told the board Convergent has been hired to oversee the county’s IT contract RFP. He outlined the planned schedule: the RFP will be released on July 31, proposals are due August 21, and evaluations and recommendations are expected by September 18. Compo said budgets are arriving and presentations will begin at the July 17 meeting and recommended delegates for the MERS conference in October.

Compo reported the Lake Margrethe Dam project is completed: sheet piles have been removed, water is moving through the dam and restoration is underway. He said an EPA grant is in preliminary stages; the work plan and several forms must be completed by July 15 and awards are expected by the end of August. The grant would run four years starting Oct. 1, 2025, if awarded.