Moira Board Approves Salt Shed Change Order and Equipment Rental, Cites Tariff-Related Cost Share
Summary
The Town Board accepted a $5,731.36 change order for Hybrid Building Solutions on the new salt/sand shed—described as a 25% share of unanticipated tariff-driven material costs—and approved a one-week $1,260 boom-lift rental from Taylor Rental for LED installation.
Get email alerts on the Construction Contracts topic
No spam. Unsubscribe anytime.
The Town Board on Oct. 14 approved Change Order Number One for Hybrid Building Solutions, increasing the salt/sand shed contract by $5,731.36. The change order was described in the minutes as Hybrid Building Solutions’ 25% share of unanticipated material costs resulting from tariffs not in place when the original bid was submitted; the board authorized the Supervisor to sign the change order on the town's behalf.
The board also authorized a one-week rental of a 60-foot articulating boom lift with jib from Taylor Rental for $1,260.00 to assist installation of LED lighting in the new salt shed. The rental was designated a sole-source procurement under the town’s procurement policy, with funds to be drawn from AA.0.5132.415 (Garage, Repairs). Both actions passed on roll-call votes (5–0).