North Mankato approves $37,243 change orders for All Seasons Arena project
Summary
Council adopted Res. No. 64-25 approving five change orders for the All Seasons Arena (Project No. 11075) that increased project costs by $37,243.52 and reduced contingency to $115,301.68.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The North Mankato City Council on July 21 adopted Resolution No. 64-25 to approve five change orders for the All Seasons Arena (Project No. 11075), resulting in a net increase of $37,243.52 to the contract and reducing the project contingency to $115,301.68.
City Administrator McCann outlined the change orders: a reduction of $24,000 from Rink‑Tec related to exterior treatments and omitted regrouting; Met‑Con increases for repainting, drywall repairs and electronic door frame updates (amount not separately itemized in the minutes); Malterer Mechanical increased by $1,735.00 for adding a hose bib and exhaust fan upgrades for code compliance; Laketown Electric increased by $2,257.97 for vestibule lighting replacement and rough‑in for future access control; and Dirt Merchant increased by $35,062.80 for soil corrections, foundation removal and backfill under the north rink seating. The council voted to adopt Res. No. 64-25 with Steiner, Oachs, Whitlock and Mayor Carlson recorded as aye.
The minutes list the total net increase and the new contingency but do not provide further budget or schedule impacts beyond the contingency reduction.