County project team flags multiple change orders that could eat contingency on transfer-station build

Todd County Board of Commissioners · March 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Todd County project leads briefed commissioners that several change orders and equipment purchases for the new transfer-station project could consume most of the 6% contingency; identified items included Minnesota Power relocation ($34,004.91), plumbing-plan revisions and added oil/water separators ($48,575), foundation reaction changes ($37,115.91) and optional interior liner panels ($66,745), plus recommended purchasing combined Bobcat/forklift equipment (~$120,000) from capital funds rather than contingency.

Project managers told the Todd County Board during a lengthy work session that a set of construction and equipment changes have emerged for the new transfer-station/solid-waste facility and that four to six items could consume most of the project's contingency.

Staff said the prime contractor's original contract with High-Tech Construction was $7.8 million, with the project approximately 68% complete based on pay requests. Stantec's design-and-administration contract remains in place. The team recapped equipment purchases and adjustments to the equipment and furniture budgets and outlined a recommended 6% contingency ($577,000).

Specific cost items presented included: Minnesota Power relocation/burying of overhead power and transformer ($34,004.91); plumbing plan-review changes required by the Department of Labor and Industry that added oil/water separators and an associated cost of $48,575; building foundation reaction-required changes tied to the pre-engineered building ($37,115.91); and an optional set of interior liner panels quoted at $66,745. Project staff recommended treating the first four items as change orders to High-Tech and paying from the project contingency, while discussing whether the interior liner panels should be advanced now or deferred. Separately, staff proposed purchasing a combined forklift/Bobcat-type machine for about $120,000 and suggested funding that purchase from the 2026 capital-improvement fund to preserve contingency for construction change orders.

"High-tech Construction, their original contract was for $7,800,000...as of our March pay request, they've spent about 5.3 [million]. So they're at 68% completion of the project," a project lead said; the team then walked through contingency items and recommended coming back with formal change-order documents. Commissioners expressed concern about drawing contingency down too far before later-stage risks are known and asked staff to return with formal board actions and possible Stantec representation to answer technical questions.