Gallagher Construction told the board geotechnical testing uncovered failing subgrade on the cut side of the new junior high; a 12‑inch cement stabilization and a Friday test strip were proposed, with estimated cost impacts to be covered from contingency.

Chris Wilson of Gallagher Construction briefed the board on an unforeseen foundation issue at the new junior high site. "The existing subgrade is not good enough," Wilson said, describing sandy, failing soils that did not pass compaction even after deeper excavation; a gravel‑lift fix came back with prices above $200,000, prompting the team to propose cement stabilization (12 inches) as the preferred remedy.

Wilson explained that Terracon will verify a test strip scheduled for Friday and will observe foundation work and a month‑long observation period afterward. Board members asked about long‑term performance and warranties; engineers and the geotechnical consultant described cement stabilization as the geotech recommendation to meet proof‑roll and compaction standards. Staff said the work would come from project contingency and noted a credit from upsizing drainage work that offsets part of the additional cost.