Commission approves revised sewer route, change order for Spring Canyon lift station
Summary
The commission approved an amendment to the lift station and sewer extension agreement with Canyon Capital Group, including a $285,350 change order and possible $125,000 developer reimbursement tied to Spring Canyon and Phantom Creek subdivisions.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Planning and Development Director Dustin Meyer told the commission Jan. 6 that construction-route challenges prompted a proposed amendment to the agreement with Canyon Capital Group, LLC to build a new lift station and extend water/wastewater mains to serve Spring Canyon and the future Phantom Creek subdivision.
Meyer said the amendment includes a change order of $285,350 and potential reimbursement of $125,000 from the developers. After discussion, the Commission voted unanimously to approve the amendment to alter the sanitary sewer infrastructure location.