Committee approves 5-year capital plan to address near-capacity portion of landfill
Summary
The committee approved a five-year Capital Improvement Plan outlining construction cost estimates needed to close a portion of the landfill that has reached capacity. The motion carried with no negative votes.
Get email alerts on the Budget topic
No spam. Unsubscribe anytime.
Landfill Director Paul Klose presented a five-year Capital Improvement Plan identifying construction cost estimates needed to close a portion of the landfill that has reached capacity. The committee voted to approve the plan (Motion Schreiber/Schindel); the minutes record the motion "carried" with no negative votes.
The minutes describe the plan as identifying the construction cost estimate needed for closure but do not state the total estimated cost or funding sources within the minutes. Committee members approved the CIP as submitted; further details are expected in project files or future meetings.