Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure Upgrades topic

No spam. Unsubscribe anytime.

Wildlife-fencing project on winter shutdown; Gate #7 electrification and food-truck power estimates presented

Fitchburg Municipal Airport Commission · January 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Gale reported the wildlife-fencing project is in winter shutdown; change order #2 includes electrification of Gate #7 and FAA Reimbursement Request #2 was submitted to MassDOT Aeronautics on Jan. 15, 2026. Manager Cornenia also presented food-truck outlet work (~$3,000) and gate power (~$6,000) quotes and asked the commission to review the CIP draft for FFY 2026–2031.

Gale Associates reported the wildlife fencing project is on winter shutdown but coordination with contractor Hastie Fence Company continues on change order #2, which would electrify Gate #7 and install a new slide gate on Cobbler Drive.

Gale confirmed FAA Reimbursement Request #2 for the fencing work was submitted to MassDOT Aeronautics Division on Jan. 15, 2026. The commission discussed the slide gate power requirements and that electrical work for the gate was not in the original contract and would be paid by the city.

Airport Manager Russ Cornenia also presented a quote from Christian Haynes to add two 120V outlets plus one 30-amp and one 50-amp outlet mounted on a pole outside the administration building for food trucks (approx. $3,000) and a separate quote to provide power to the new slide Gate #7 (approx. $6,000). Chair Raymond reminded commissioners to review the draft Capital Improvement Program (FFY 2026–2031) and bring comments to the next meeting.