Board awards Phase 1 site‑work and roofing contracts; staff says bids came in under estimate

Eden Central School District Board of Education · March 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved Phase 1 capital contracts: Foam and Asphalt Paving Corporation for site work (total $2,064,500) and Weaver Metal and Roofing for roofing (total $4,854,000). District staff said bids were about $2.6 million below earlier estimates and chose a 30‑year warranty roof option to stagger future replacements.

The board voted to award the Phase 1 site‑work contract to Foam and Asphalt Paving Corporation (base bid $1,585,000; alternates $450,500 and $25,000; total award $2,064,500) and the roofing contract to Weaver Metal and Roofing Incorporated (base $4,112,000; alternate $3,742,000; total award $4,854,000). Staff noted the district elected a higher‑quality roof with a 30‑year warranty to space future replacements.

District staff told the board the bids came in significantly below earlier planning estimates — "incredibly well to the tune of about 2,600,000 less than we had planned for," — and described how parking‑lot and roofing work would be sequenced over the coming summers. The board approved construction material inspection and testing services from Anchorus Group and authorized related appointments; all motions carried by voice vote.