Academy ISD Bond 2021 update: PAC concrete pour set for Jan. 30; Band Hall nearly complete

Academy Independent School District Board of Trustees · January 29, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Architects told the board that concrete for the Performing Arts Center will be poured Jan. 30 at 8:00 a.m., seating installation is scheduled for Feb. 17, and Band Hall awaits doors and flooring with overall completion expected by Spring Break.

Representatives from Weaver & Jacobs / Claycomb Architects, Randy Boone and Christine Walker, told the Academy ISD Board on Jan. 29 that major work on Bond 2021 projects is advancing. The concrete slab for the Performing Arts Center (PAC) was scheduled for pouring on Jan. 30, 2025 at 8:00 a.m., seating installation was slated for Feb. 17, and flooring deliveries were expected the following week.

Architects reported AV testing planned and noted an "access point" issue that could push parts of final work to mid-February. The Band Hall is largely complete and is waiting only on doors and flooring; the architects stated completion no later than Spring Break. Trustees received the construction timeline as part of routine bond project updates and asked staff to continue monitoring the access-point delay to avoid schedule slippage.

The board’s public minutes recorded the specific dates and construction milestones provided by the architects; no contract changes or additional funding requests were presented during this update.