Bond project on schedule after ceremonial groundbreaking, district told
Summary
Contractor Britt Williams told the Aquilla ISD Board that a ceremonial groundbreaking occurred earlier that day, the building pad is nearly complete, surveying for piers will follow, and the contractor is targeting an early June slab pour; an extra expense was noted for Cougar Drive due to TxDOT requirements.
Get email alerts on the Bond Project topic
No spam. Unsubscribe anytime.
Britt Williams updated the Aquilla ISD Board on the district's bond construction project, saying the ceremonial groundbreaking took place earlier in the day and that the building pad is nearly complete. He said surveying for piers will follow and the contractor is targeting an early June slab pour.
Williams told the board that work on Cougar Drive has incurred an additional expense because of Texas Department of Transportation engineering requirements but said the project remains on schedule. The presentation covered sequencing for the next phases and confirmed current timelines for slab and pier work.