Bastrop ISD reports progress on bond projects including Adelton Elementary and Mina rebuild

Board of Trustees, Bastrop Independent School District · January 28, 2025

Summary

Construction and design updates: Adelton Elementary is reported 25% complete, Mina Elementary rebuild is 2% complete, middle school weight rooms are nearly finished, and high school classroom wing is in design phase.

Lee Raspberry, Director of Construction & Planning, updated the board on the district’s 2021/2023 bond program status and key facilities projects.

Raspberry reported near-complete weight rooms at Bastrop and Cedar Creek Middle Schools (99% complete), Adelton Elementary at 25% complete, Mina Elementary rebuild at 2% complete, and the Bastrop High School classroom wing in the design phase. He said the new Police and Operations Facility construction had begun this month and other additions and renovations were on schedule.

Board members received the facilities & operations report and asked clarifying questions. Staff will continue to provide regular bond updates as projects proceed.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source