Summary
The district engineer presented repair costs for damaged wiring and raising seven to eight irrigation heads; the board approved an Irrigation Concepts change order with a not-to-exceed amount of $15,000.
Get email alerts on the Infrastructure Maintenance topic
No spam. Unsubscribe anytime.
District Engineer Charlie Krebs presented a revised scope for the Seaside & Master Drainage Project and noted ancillary irrigation costs related to damaged wiring ($4,002.50) and raising seven to eight irrigation heads at roughly $1,300 each. MRI expects the drainage work to begin within two to three weeks.
On a motion by Supervisor Kurt Blumenthal and seconded by Chair Bob Schultz, the board approved the Irrigation Concepts change order to repair the wiring and raise irrigation heads in a not-to-exceed amount of $15,000.