Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Bryan ISD says 2020 bond projects nearing completion; estimates $2.23 million in savings
Summary
District officials reported progress across the $175 million 2020 bond program, including O.W. Sadberry Phase II expected by Spring 2025 and the opening of the Ruby Haliburton Auxiliary Complex; administrators estimated about $2,232,549 in bond savings as projects come in under budget.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Assistant Superintendent of Business Services Kevin Beesaw reported that the district’s $175,000,000 2020 bond program is progressing across multiple categories, including safety and security, construction and additions, priority maintenance and mechanical/plumbing upgrades. He said O.W. Sadberry’s Phase II — which includes a play and park area and a walking trail — is expected to be complete by Spring 2025, and the Ruby Haliburton Auxiliary Complex is already in operation following a Sept. 23, 2024 dedication.
Beesaw told the board that many projects are nearing completion and that, because of careful fund monitoring and projects coming in under budget, the administration expects approximately $2,232,549 in bond savings. The administration listed fencing, shade structures and classroom additions among near-complete projects.
