Staff: IDOT/ITEP pay apps pending; village liability unclear for Cherokee Street repairs
Summary
Staff reported two IDOT/ITEP pay apps totaling just over $84,000; the village's share depends on grant eligibility (about 20% where applicable) and outstanding non‑grant items could raise the village's final bill; staff is awaiting state confirmation.
Get email alerts on the Streets topic
No spam. Unsubscribe anytime.
Staff reported two recent pay‑app estimates submitted to IDOT for the ITEP project (pay apps 10 and 11) that together total just over $84,000. The village's estimated share for grant‑eligible work is about 20 percent, but staff warned some charges—such as railing repair noted on a pay app—may be non‑grant‑eligible and, if so, would increase the village's liability.
"Based on the two pay ups, I think everything's covered by the grant yet... It could be 20,000. It could be 60,000. I don't know," staff said, summarizing current uncertainty. Staff has sent follow‑up emails to IDOT and the contractor but had not yet received final billing confirmation; the board asked staff to withhold approving additional outgoing expenses until the total liability is clarified.
Board members recalled historical numbers in the packet (staff cited $545,000 paid to date and an earlier estimated total near $606,000) and asked for a clearer reconciliation so they can plan appropriations and potential contingency funds.