Geneseo updates gym deconstruction, plans PA and safety upgrades with COPS grant seed money

GENESEO CENTRAL SCHOOL DISTRICT · April 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported gym floor deconstruction progressing into an abatement phase, vendor quotes being sought for PA/safety upgrades funded largely by a COPS grant that requires $108,000 in seed money, and timelines aiming for summer work.

District presenters updated the board on ongoing capital work and planned safety improvements.

On the capital project, staff said gym floor deconstruction is complete down to an old rubberized layer and that abatement (including removal of mercury flooring) and subsequent locker‑room work are next steps. "The deconstruction of the gym floor is going well so far... they've gotten down to the rubberized portion that needs to be removed," the presenter said and described a sequence of phases and modest challenges typical of older buildings.

On safety, staff said the district applied for and was awarded a COPS grant to support PA system replacement and other security enhancements, but the grant requires district seed money. Staff recited a seed‑money figure of $108,000 to leverage roughly $354,000 from the grant in total, characterizing the work as a one‑time expenditure to install visual signage, strobes and an upgraded PA integrated with existing infrastructure. The district said it is obtaining multiple vendor quotes and aims to begin work possibly this summer pending contract awards.