Boulder Path construction on schedule; residents urge better pedestrian signage and flagging
Summary
Town staff reported Boulder Path construction is on track for binder coat by Oct. 9 but residents urged clearer pedestrian detours and staffing after cyclists and pedestrians entered active work zones; town will add signage, consider DPS detail and use of an electronic message sign.
Get email alerts on the Boulder Path topic
No spam. Unsubscribe anytime.
Town staff told the Select Board Aug. 5 that construction work on Boulder Path is on schedule, with plans for binder coat and curb work aimed around Oct. 9. Staff said in-ground infrastructure work is near completion and the road will be closed daily for the next two weeks to speed work.
Several residents described near-misses as cyclists and pedestrians entered work zones when the road was temporarily reopened on non-work days; one resident asked for an on-site person to direct people and for better signage. The chair responded: “Message received, Craig. We’re gonna—we’ll do something about it.” Staff said they would ask DPS to provide a detail at the site and deploy an electronic message sign at intersection approaches to indicate a pedestrian detour.
The board asked staff to check pedestrian detour signage at key approaches (West Branch and the ski-lift bridge) and to coordinate with local bike-rental operators and the resort to distribute detour maps. Staff noted the town cannot afford a 24/7 detail but said targeted staffing at peak times could be arranged.