Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Facilities Planning topic

No spam. Unsubscribe anytime.

Lake Travis ISD reviews High School #2 preliminary design, enrollment projections and Elementary School #8 timing

Lake Travis Independent School District Board of Trustees · November 20, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District architects presented a preliminary two-phase design for High School #2 (Phase One capacity 1,500 students; Phase Two adds 500) and administrators reviewed October PEIMS counts and demographic projections that will affect when Elementary School #8 opens.

At the Nov. 20 board meeting Lake Travis ISD received a preliminary design presentation for High School #2 and an enrollment update tied to the district’s PEIMS October count and a January 2024 demographic study.

VLK Architects described a two-phase approach for High School #2: Phase One would be built to accommodate 1,500 students and Phase Two would add capacity for an additional 500 if and when needed. The design reflects earlier Board decisions and recent county land purchases within LTISD boundaries. Administrators indicated the Phase One sizing is intended to match projected near-term enrollment growth while leaving capacity for later expansion.

Separately, the district presented required PEIMS enrollment figures for 2024–25 and shared projected enrollment trends that could influence the schedule for opening Elementary School #8. The minutes note the presentation was for discussion only and that any action related to construction timing or bonding would follow additional planning and board consideration.