Board hears capital-project and facilities updates: sidewalks, paving, lockers, windows and Blue Light system
Summary
Superintendent TheriJo Snyder updated the board on capital work including an elementary sidewalk, bus-garage paving, phased locker installs, bleachers after basketball season, skylight work over break, Blue Light emergency system installation, elementary window replacements and gym-floor protection.
Get email alerts on the Capital Project topic
No spam. Unsubscribe anytime.
Superintendent TheriJo Snyder provided a rundown of capital-project tasks and timetables at the Oct. 2 board meeting. Items discussed included planned work on an elementary sidewalk, bus-garage paving, a second shift of locker installations, bleachers to be replaced after basketball season, skylight repairs scheduled for school break, installation of a Blue Light emergency notification system, phased elementary window replacements (one per day planned the week after the meeting) and protecting the elementary gym floor during construction.
Snyder said some items (for example, bleacher replacement) are scheduled to avoid interfering with athletics and noted a letter would be sent to parents about an upcoming evacuation drill to the Cherry Valley Community Center. No cost figures or contractor names appeared in the transcript; the discussion focused on logistics and sequencing.