District and vendor outline phased construction schedule, plan to limit school‑year disruption
Summary
Presenters said work would be phased over summers and through brief classroom rotations during the school year; drilling of the well field would likely wait until school is out and substantial completion is targeted for December 2027.
Get email alerts on the Construction Schedule topic
No spam. Unsubscribe anytime.
Presenters described a phased approach to keep classroom disruption minimal: most heavy work (well drilling and central plant installation) would be scheduled in summer windows and the team expects to phase classroom work one or a few rooms at a time during the school year.
On the schedule, presenters said a positive referendum and SED approvals would allow construction to begin the following summer; they set a goal of substantial completion around December 2027 and emphasized coordination so drilling would not start until students are out. “We probably wouldn't start drilling the wells until school is out,” one presenter said; another added, “We can start the day after graduation.”