Town updates: Bristol West waterline progress; Bristol East becomes candidate for 50% state forgiveness; library remediation aided by $300K+ in grants
Summary
Town Administrator Gregory Faust reported Bristol West water-line work has moved from Elm to Taylor Street, Bristol East is second on the lead-service-line list and may qualify for 50% state forgiveness, and the library asbestos remediation is complete with more than $300,000 in additional grant funds obtained.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Town Administrator Gregory Faust updated the Selectboard on several infrastructure and facility items. He said "Bristol West water line construction is progressing, and have moved from Elm Street to Taylor Street." He also reported that the Bristol East water-line project "has placed second on the lead service line list, indicating the potential for 50% forgiveness for State funding of that project."
Faust said asbestos remediation at the library is complete and PCB work is finishing, and that the town had obtained an additional $300,000+ in grant funds to complete those elements of the renovation. Faust discussed the town's bonding position, noting the town is currently under-bonded and that combining the West and East water-line projects could produce beneficial quotes, but would require State approval.