Construction progresses at McCamey ISD gym and high school, board hears update

McCamey ISD Board of Trustees · December 11, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Gallagher Construction reported cabinet and floor work finished in the gym, with roofing and painting underway; high school masonry, brickwork, auditorium steel and framing are in progress.

Mark Miller of Gallagher Construction updated the board on ongoing work at district facilities. In the gymnasium, cabinet installations and floor installation are complete and roof work and painting are underway. At the high school, contractors are completing concrete masonry unit work, installing brick, erecting auditorium steel, and installing framing and roof systems.

No formal board action was recorded on the construction update; the report was provided for the board's information and to record project progress in the minutes.