Council approves $591,604.64 contract for Unit 7 turbine and generator inspection

City of Fremont City Council · April 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council awarded a competitive contract to HPI for an inspection and overhaul of Unit 7 at the Laundy Wright Generating Station; staff said HPI was the lowest bidder and work is scheduled for fall 2026.

Utility Manager Jeff Shanahan recommended awarding the contract for Unit 7 turbine and generator inspection to HPI for $591,604.64 after a formal bid opening that produced four bids. Shanahan said the units are base-load and undergo major overhauls approximately every 40,000 hours of operation.

"HPI was the lowest bidder," Shanahan said. He told the council the work would take place in fall 2026 and that staff recommended awarding the contract. The council approved the motion 8'0to'00.