Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
New Nederland High School near completion; open house scheduled for Oct. 28
Summary
Contractors reported the new high school project is in final punch-list and finishing stages, with grounds prepped for an Oct. 28 open house and a small set of exterior and interior punch-list items remaining.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Contractor representatives updated the board on bond and new-campus construction. Brad Hughes (IBI/ARCADIS) said bond-related work is primarily in the punch-list and fact-checking phase, with a few outstanding items at the old high school and the stadium track still to be wrapped up.
Ty Neild reported progress on the new Nederland High School and said grounds would be prepared for an open house on Oct. 28. Remaining work included installation of 3–4 light poles, striping of sidewalks, exterior trim and downspouts, fencing around the pond, and interior finish work such as the welding shop and owner-provided equipment hookups. Demolition work at the old campus has begun. The minutes record these details but do not include verbatim contractor quotes.
