County names Pipestone tower interim solution while WOJB status resolved; target to go live by October
Summary
Officials said a July design meeting reviewed sites and signal paths and that the county will rely on the Pipestone tower as an interim replacement for the WOJB tower; the system is targeted to be up and running by the end of October though some indoor 'talk-back' coverage in the northeast may be spotty.
Get email alerts on the Communications Infrastructure topic
No spam. Unsubscribe anytime.
Project staff reported on a July 24 design meeting with Gencom that reviewed sites, signal capacity, path profiles and terrain, and concluded the county can achieve reliable outside coverage using the Pipestone tower as an interim option while the future of the WOJB tower is decided.
"The whole system will be up and running by the end of October before snow flies," one project lead said, but he and other staff cautioned that indoor talk-back coverage in a small northeast corner of the county might be spotty while the interim configuration is used. The county aims to complete concrete foundations in the weeks ahead and erect steel in October so the system can go live.
Officials noted that if changes to the WOJB structure require code upgrades, the tower owner could ask the county to contribute to the cost; they said such terms would be negotiated at that time. Federal grant opportunities for the project exist, and the committee emphasized the timeline as a priority.