Council approves 85‑day time extension for West Mulberry Street project
Summary
Parish President Miller reported and the council approved Change Order No. 2 for the West Mulberry Street extension, adding 85 calendar days because of weather and permit delays and moving expected completion to Sept. 2, 2026.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Parish President Miller presented Change Order No. 2 for the West Mulberry Street extension, describing it as an "extension of time only for the rate, weather related days and some, permit delays that we had." He told the council, "They're adding 85 calendar days to the completion, which is now expected 09/02/2026." A council member moved to approve and another seconded the motion.
The council approved the extension by roll-call vote. A councilmember who visited the site praised the work as "a big improvement," and staff said the extended schedule reflected uncontrollable weather and permitting delays rather than design changes.