Engineer reports Phase II ROWs secured; Chub Run and Phase IV sewer projects remain on schedule but face delays
Summary
The engineer reported 28 of 34 rights-of-way secured for Phase II AMD/AML, submitted an environmental assessment Oct. 23, 2025, aims to put the project out to bid by year-end, and said the Chub Run sewer extension likely will be delayed to the end of the year; Phase IV awaits PSC and DEP approvals to connect at Sandy's Hardware station.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
At the Oct. 28 meeting the engineer's written report provided updates on multiple sewer and mine-reclamation projects. The Phase II AMD/AML project has secured 28 of 34 rights-of-way and the environmental assessment was submitted to the Office of Surface Mining on Oct. 23, 2025; the engineer said the project is being aimed to go out for bid by the end of the year.
The Chub Run sewer extension contractor was scheduled to start around Nov. 1 but the engineer anticipated the likely start would slip until the end of the year. The Phase IV sewer project is waiting on approvals from the Public Service Commission (PSC) and the Department of Environmental Protection (DEP) to make a connection at Sandy's Hardware station. No binding dates were set at the meeting.