Selectboard reviews 55 Route 13 office move costs and defers Daniels Academy repairs

Town of Brookline Selectboard · June 8, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff have moved into temporary Town offices at 55 Route 13 with about $54,180 paid to date and anticipated total costs near $80,000; the board reviewed Morin's Daniels Academy roof-support proposal but asked for a two-phase plan and postponed action.

The Selectboard reviewed progress on the town office move to 55 Route 13 and discussed associated costs on June 8. Staff have settled into the space; the board reviewed a spreadsheet of $54,180 paid so far and estimated overall costs near $80,000. Board members noted town-office requirements are stricter than standard commercial space and that funds may come from the Town Hall investigation allocation ($300,000) or from InvestNH grant proceeds tied to Brookline Woods.

On Daniels Academy, the board examined a proposal from Morin to replace temporary roof-support beams with permanent beams fixed to exterior walls. Members expressed concern that opening walls could reveal additional work and costs; the board requested a two-phase proposal (inspection first) and postponed a decision to the next meeting. Ads for a Town Hall project manager have been posted and proposals are due by the next meeting.