Trappe council unanimously approves $63,400 emergency diesel generator purchase with ARPA funds
Summary
At a Sept. 11 special meeting, the Trappe Town Council approved using ARPA funds to buy a diesel generator and hire Bilbrough Electric for installation, citing the vendor's local presence and existing contract. The total approved amount was $63,400.
Get email alerts on the Emergency Generator Purchase topic
No spam. Unsubscribe anytime.
The Trappe Town Council on Sept. 11 unanimously approved using American Rescue Plan Act (ARPA) funds to purchase and install a diesel generator at the town water tower for a total of $63,400. The motion, moved by Commissioner Jeremy Newnam and seconded by Commissioner Michael Sullivan, passed without opposition.
Town Administrator Erin Braband told the council staff contacted five companies for emergency replacement quotes after the town's existing propane generator failed. The approved package is built from Kelly Generator's quote for a Generac 130 kW unit ($54,500) combined with Bilbrough Electric's electrical work quote ($8,900), for the $63,400 total recorded in the minutes. The council cited Kelly Generator's local presence, the town's existing contract with the company for generator services, and familiarity with Trappe infrastructure as reasons for choosing the vendor despite other competitive bids.
Minutes list two General Power quotes received the same day: a Perkins 130 kW unit for $52,051 plus shipping from Florida, and an in-stock Perkins 150 kW unit quoted at $55,573 plus $2,273 shipping (total $57,846). Bilbrough Electric noted it based its $8,900 estimate on Kelly Generator's specifications and would need to perform a site visit to provide a comparable quote for General Power's specs.
The council recorded the meeting start at 2:00 p.m. and adjourned at 2:38 p.m.; Erin Braband signed the minutes. The approved emergency purchase will proceed under the town administrator's and water/wastewater operator Shawn Lane's oversight, with Bilbrough scheduling follow-up site work and any necessary coordination with Kelly Generator.