Council ratifies multiple change orders for 44 Frederick and retools firing-range procurement
Summary
Council ratified several change orders and approved a large credit related to 44 Frederick public-safety facility work, and voted to remove the donor-funded firing-range scope from the ECI contract so it can be competitively bid and installed separately.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Council ratified several project change orders for the 44 Frederick public-safety facility and approved a credit related to redesigning a planned masonry wall into a fence after extensive underground utilities were discovered. The meeting record listed PCO #19 for $9,639, PCO #20 for $9,308 and PCO #21 for $6,004; council approved the items as recommended by the architect and staff. Later, council approved a credit (PCO #22) in the amount of $61,433 tied to substituting a fence where a masonry wall had been planned.
Public works staff explained the masonry requirement could not be supported without heavy foundations because of a "rat's nest of utilities" in the proposed wall location; switching to fence posts reduced foundation needs and yielded the credit. On the firing-range work at the public-safety facility, staff said donor funding exists but arrives across multiple years, complicating RACP accounting. To comply with grant and procurement rules, staff proposed—and council approved—backing the firing-range scope out of the ECI contract ($593,775 credit) and preparing a separate competitive bid package for the firing-range equipment-installation to control costs. Council also authorized staff to advertise that equipment-installation bid.