DRB approves curb‑cut shift at 227–229 Pearl Street to avoid utility pole

Essex Junction Development Review Board · June 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a major site plan amendment for 227–229 Pearl Street to relocate the curb cut to avoid an existing utility pole. Applicant Gabe said the survey missed the pole and shifting the driveway was faster than asking Green Mountain Power to move the pole.

The Development Review Board approved a major site plan amendment to move the curb cut at 227–229 Pearl Street to avoid an existing utility pole, allowing the applicant to maintain parking and emergency access while shifting the driveway alignment.

The applicant, Gabe, told the board his engineer missed the pole on a recent survey after Pearl Street repaving; he said moving utilities would be “substantial” and time‑consuming because multiple services (power, internet, phone, cable) run on the pole and Green Mountain Power owns it. Gabe said shifting the driveway a few feet onto his property was a faster, practical fix.

Staff and the city engineer confirmed the proposed driveway shift keeps adequate parking and that the fire department can operate within the adjusted geometry. A board member asked about corridor improvements and speed limits; staff said the city council has endorsed a Pearl Street multimodal scoping study that calls for a reduced speed limit and shared‑use path. The board moved, seconded and approved the amendment with staff conditions.

“As I became aware of it when I returned through Chris… my engineer missed the one of the poles,” Gabe said during the hearing. The board voted in favor and the motion carried.