Committee recommends $20,000 increase to owner-adviser contract for Tahoe Cedars reconstruction
Summary
Julie Ryan asked the committee to recommend increasing Larry Johnson's owner-adviser contract from $24,000 to $44,000 to fund his continued support through 2026 for the Tahoe Cedars water system reconstruction project; staff said the expense is budgeted and likely to be extended annually as needed.
Get email alerts on the Professional Services topic
No spam. Unsubscribe anytime.
Julie Ryan, senior civil engineer, asked the committee to recommend that the board approve Amendment No.1 to the professional services agreement with Larry Johnson, raising the contract not-to-exceed amount from $24,000 to $44,000 to continue his role as owner adviser on the Tahoe Cedars water system reconstruction project through 2026.
Ryan said Johnson has been advising the district since September 2024 and that the additional $20,000 is budgeted to fund his continued support. "Mister Johnson has been serving as an owner adviser to the district on the Tahoe Cedars project since September 2024, and he's been providing expertise on the progressive design build process," she said.
Staff recommended the item for the board consent agenda and indicated they expect to return annually to extend the contract as needed through the project term.