Neighbors and commissioners press developer on water supply; applicant cites a wholesale term sheet and options
Summary
Public commenters and commissioners pressed TriMark and staff about water availability for the 387‑acre PDD. Applicant said it has a wholesale term sheet with a wholesaler (Texas Water Supply) and is seeking a retail provider; commissioners said proof of retail service is typically required at planning stage, not zoning.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Water availability and the identity of a retail water provider became a focal point of the PDD hearing. Linden Sisk told the commission the property is inside a CCN area currently held by Texas Water Company and asked when applicants must provide proof of water availability. Sisk said the CCN holder had placed a hold on water for other subdivisions and asked when a water availability report would be provided.
Applicant representatives and staff replied that the project team has a term sheet with a wholesale water provider (identified in the hearing as Texas Water Supply) and is seeking a retail provider or other mechanisms (CCN transfer, MUD, or qualified third‑party). As Brooke Lynn Hall (staff) explained, municipalities generally can require proof of a retail water provider at the planning stage, not at the zoning/PDD stage. The applicant stated, "We have a path forward for water today," while acknowledging that final retail agreements and TCEQ permitting remain to be completed. Commissioners asked for documentation for the council packet and warned that a missing retail provider could stall platting at the planning stage.