Staff recommends contract to Baldoni Construction for Dianne Feinstein West Shore Tahoe Trail Segment 1
Summary
Staff recommended awarding the construction contract for the Dianne Feinstein West Shore Tahoe Trail Segment 1 to Baldoni Construction as the low responsive bidder at $2.4 million, with preauthorization for up to 10% ($242,000) in change orders; construction is estimated at about $3.5 million with $2.2 million in grant funds secured.
Get email alerts on the West Shore Trail topic
No spam. Unsubscribe anytime.
Philip Tapia, construction project manager, told the committee the project received six bids and staff are recommending the board "enter into contract with the lowest responsive bidder, Baldoni Construction" at a bid price of $2,400,000 and asked the board to preauthorize the general manager to approve up to 10% in change orders, about $242,000.
Tapia said the construction base is estimated at roughly $3,500,000 and that $2,200,000 in grant funds have been secured to offset construction costs. During follow-up questions a board member asked where the remainder of the grant funding would come from; staff said the balance includes Transient Occupancy Tax (TOT) funds and multi-year carryovers. Board members indicated they were comfortable placing the item on the consent calendar for approval.
No formal roll-call vote was recorded in the transcript. The item was presented as a recommendation for consent; the transcript does not record a formal motion, mover, second or a vote tally.