Board praises Noble Panels donation as FFA barn nears completion
Summary
District staff described the nearly finished FFA barn project, saying Noble Panels will donate $16,000 in custom panels and the district will cover the remainder of an estimated $50,000 project.
Get email alerts on the FFA Facilities topic
No spam. Unsubscribe anytime.
Staff updated the board on the FFA barn project and described in detail the custom work, lockers for student feed storage and an anticipated timeline for finishing touches like garage doors. "Noble Panels is going to donate, $16,000 worth of this project," the staff member said, and staff reported the district expects to write a check for about $30,000 to cover the remaining cost; overall project cost was estimated at roughly $50,000 in the discussion.
Staff said the barn already has a concrete pad, perimeter fencing will be ordered July 1 and a banner and PR plans are in the works to recognize the donor and the district partnership. The board was asked to approve the purchase and bid award for the custom panels and lockers; staff recommended approval.