Board approves $7,920 extra to contractor after unplanned fuel-tank work
Summary
Town approved $7,920 in additional contractor costs after replacement of single-wall fuel tanks uncovered unanticipated work: MaineCare delivered tanks without coordination and a slab had to be poured; Belgian Trucking performed the work and the board approved the extra expense 3–1.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The chair told the board that the town replaced single-wall fuel tanks with double-wall tanks, removing a rotted containment system and avoiding a potential environmental leak. He said coordination failures — including MaineCare delivering tanks without notice and lack of response from the highway superintendent — led to unanticipated contractor and concrete costs that amounted to $7,920.
"I think we dodged a bullet by getting these installed," the chair said, describing how Belgian Trucking removed the old enclosure, poured a concrete slab, and handled temporary tank transfers. The chair asked the board to authorize $7,920 to cover additional contractor expenses; the motion passed 3–1 and the chair said the town will pay the amount the following morning. The chair also noted the electronics and key-fob fuel-dispensing controls remain to be configured and will require cooperation from the highway department.