Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure topic

No spam. Unsubscribe anytime.

Albany Avenue pedestrian and water‑main projects near completion; financing and final items remain

Kinderhook Village Board of Trustees · August 14, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees heard that the Albany Avenue Pedestrian & Bicycle Improvement Project and the Albany Avenue Water Main Upgrade are parallel efforts with separate funding. The water‑main upgrade is 92.2% complete; Birdsall Construction invoiced $211,629.60 and total contract cost stands at $694,884 after $21,070 in change orders.

Trustee James Mark Browne gave a detailed status report on the Albany Avenue projects, emphasizing that the pedestrian/bicycle improvements and the water‑main upgrade are separate projects with independent funding and requirements. He said NYS Parks, Recreation and Historic Preservation issued a letter finding "No Adverse Effect"; NYSDOT forwarded that to the Federal Highway Administration and FHWA concurrence was received in mid‑August 2024, clearing the way for final design and construction approval.

On the water side, the Albany Avenue Water Main Upgrade was reported at 92.2% complete. Birdsall Construction submitted an invoice for $211,629.60, which the board approved, bringing the reported completed net value to $634,457.34. Four change orders totaling $21,070 (about 3% of the original bid) raised the low‑bid contract to $694,884. Trustee Browne said only hydroseeding and final closeout tasks remain; further decisions about Williams Street improvements will depend on Environmental Facilities Corporation (EFC) grant/loan determinations.