Colton council approves small increase and withholds payment on Phase 4–5 sewer work pending seeding

City of Colton City Council · January 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Change Order #3 (+$2,340.75) for Alliance Construction LLC and withheld $5,000 from Pay Request #7—paying $16,921.34 now—pending spring seeding for Phase 4 & 5 sanitary and storm sewer improvements.

Banner Associates presented an update on Phase 4 & 5 Waste Water and Storm Sewer improvements. The council approved Change Order #3, increasing Alliance Construction LLC’s contract by $2,340.75 (motion by Vande Voort, seconded by Bunjer). The motion passed with all members voting aye.

Council then considered Alliance LLC Pay Request #7 and approved withholding $5,000, authorizing payment of $16,921.34 to the contractor until potential spring seeding is completed (motion by Wochnick, seconded by Evans). The action was recorded as approved by unanimous roll call. Weston Blasius presented the materials and staff noted the withholding was tied to ensuring required restoration work (seeding) is completed.