Board approves $101,700 pay application to Kelsey Excavating; wastewater project due end of April

Village of Dakota Board · March 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Village of Dakota approved Pay Application #6 for $101,700 to Kelsey Excavating and was informed that the wastewater treatment facility project is scheduled for completion by the end of April 2025. The board also approved a $1,100 engineering invoice.

The board voted to approve Pay Application #6 from Kelsey Excavating for construction services in the amount of $101,700 (motion by Jeremy Knox, second by Ken Vrazsity; motion carried). President Jon Riley distributed a schedule from Kelsey Excavating and told the board the wastewater treatment facility project is expected to be completed by the end of April 2025.

Separately, the board approved payment of a Gallagher Engineering invoice for engineering services totaling $1,100 (motion by Jeremy Knox, second by Ken Vrazsity; motion carried). The meeting record shows account balances and employee timesheets were reviewed with no substantive discussion recorded.